Show TOC
EnjoySAP - New Maintenance Transaction for Production Versions
Scope of Functions
Until now, you could edit production versions either from the relevant
material master record or from the master recipe. In both cases, you
had to deal with certain restrictions with regard to the maintenance.
A separate maintenance transaction for production versions is now
available, which you can also use as an initial screen for master recipe of material (BOM) maintenance. The new transaction has the
following advantages:
- You can create a worklist for any number of production versions.
- In this worklist, you can edit production versions in mass processing or individual processing.
- From the worklist, you can directly call up all activities, such as
creating, copying, changing, displaying, and deleting production versions.
- You can create any number of production versions and assign change
numbers to them independent of recipe maintenance. In this way, the approval procedure has been simplified considerably.
- If a master recipe has been assigned to a production version as its
detailed plan, you can navigate to recipe maintenance from the production version to create or edit the master recipe and BOM. This
means that you can now access production versions, master recipes, and BOMs from the same screen.
If a change number has been assigned to a production version, this
number is also valid for recipe and BOM maintenance from within the
production version. This enables you to use an approval procedure in the same way for all related objects.
To access the new transaction from the R/3 menu, choose Logistics ->
Production - process -> Master data -> Production versions
or Logistics -> Production -> Master data
-> Production versions.
See also
SAP Library, section PP - Production Planning - Process Industries -> Master Recipes
-> Master Recipe Maintenance -> Material Data Maintenance