Perform Time Transfers

In this step, you set controls for time transfers.

Example

An employee has a

flextime balance of 5 hours, but his or her compensation time balance is 3 hours short. In the Time Transfer Specifications infotype (2012), you enter atransfer specification of 3 hours that posts flextime to compensation time. You want to use the transfer rules you defined in the Time Transfer section.

Requirements

You have set the rules for time transfer types in the Time Transfer section.
See also Set rules for transfer to time types , Set rules for transfer to wage types , and Set rules for transfer to absence quotas.

Standard Settings

In the standard SAP R/3 System, transfer is controlled according to the rules you defined in the Time Transfer section.

Activities

    1. Decide whether you want to control the transfer of time balances using the rules set in the "Time Transfer Types" section, or using a personnel calculation rule.
    2. If you want to use a personnel calculation rule, enter the name of the personnel calculation rule as the first parameter of function P2012.

Further Notes

Personnel calculation rule TR20 is a reference for time transfer processing. You can modify TR20 as you require. Please copy personnel calculation rule TR20 to ZR20, and make any necessary modifications in the copied version.