Displaying the Capacity Load in the Work Center Hierarchy 
On the
SAP R/3 screen select Logistics ® Production ® Capacity planning.On the Capacity Planning screen, select Evaluation ® Work center view ® Load.
On the Capacity Planning: Selection screen enter the following data:
Field |
Data |
Work center |
1310 |
Plant |
3000 |
Select Continue Enter.
The system displays the work center capacity.
Select Standard Overview to display a graph of the capacity.
On the

To see the details of the capacity load for a designated time period, select a period and press Capacity details/period.
Return to the main
SAP R/3 screen.End of the Process Chain.