Process Work Time Events
In this step, you schedule jobs to post work time events and transfer the corrected actual times to Logistics.
Example
You want to process work time events once daily, overnight.
Notes
Posting work time events can be started by a specific event. To do so, schedule the starting time After event
in the Create session to run background job in report SAPCDT46. Use the
event SAP_KK1_UPLOAD_FINISHED with parameter 3.
Activities
1. Decide which parameters should be used to start the reports. Then define appropriate variants for the reports.
2. Define a job to start the reports to process the session as follows:
- Choose an appropriate job name.
- Choose an appropriate job class.
- In the Variant field, enter the name of the variant you have created.
Further Notes
- A job you schedule in the test system is not transported to the
production system. You must schedule the job again in the production system.