Replenishment Using Production Orders 

Use

You use this function when you process your in-house production with production orders. When the demand source sets the kanban to EMPTY, the system creates a production order for the kanban quantity for the supply source.

Prerequisites

? Scheduling

As a rule you work with KANBAN with forward scheduling. The production order type PPK1, which contains all necessary settings, is preset in the SAP standard system for KANBAN.

To determine backward scheduling (for event-driven KANBAN) enter the standard production order type PP01.

? Automatic routing selection

For this, you maintain the automatic selection of the routing as well as the selection ID for automatic selection in the order type.

You make these settings in Customizing for production orders: Master data?Order ? Define order types. These allocations are already available for the standard order types.

Actions

  1. You set a kanban to EMPTY or you generate an event-driven kanban.
  2. The system creates a production order that (depending on the settings in Customizing) is automatically released and printed.
  3. The empty kanban or the information is transferred to the supply source.
  4. Once the order has been completed, the supply source backflushes the quantity produced. In Customizing, you can link the backflush to the goods receipt posting. This provides the following options:

If the goods receipt is posted before the backflush, the system sets the kanban status to FULL, but the backflush is not carried out automatically. Then when you backflush, the system recognizes that the goods receipt has already been posted and does not post a second goods receipt.

The costs incurred in production are posted to the production order.