Replenishment Using Run Schedule Quantities 
Use
You use this function when you produce the necessary material yourself, by means of repetitive manufacturing. As soon as a kanban is set to EMPTY the system creates run schedule quantities for this material, i.e. planned orders for repetitive manufacturing, and this triggers production.
Prerequisites
In this process the system posts the costs incurred in production to the cost collector. Refer to
Actions
1. You set a kanban to EMPTY.
2. The system creates a run schedule quantity.
3. The kanban or the information is transported by the demand source to the supply source. If necessary the card is reprinted at the supply source or it is attached to the kanban.
4. The supply source receives the information on all the empty containers by means of the kanban or via the kanban board.
5. After the container has been filled by the supply source, you have three options:
Also read the section
Carrying Out the Kanban Backflush.

If you manually change the component list of the run schedule quantity (in order to change component quantities for example), the system automatically carries out the backflush with the changed run schedule quantity data when the kanban is set to FULL.

If the status is set to FULL or the backflush transaction is posted without component processing, then the system explodes the current BOM. If you want to change components, then you must use the backflushing function or you can manually change the run schedule quantity. In so doing, you access the component screen.