Smoothing the Dependent Requirements 

In the planning run, the system takes for granted that all components are available to start producing the order, that is, on the order start date of the pegged order. It then plans the dependent requirements date using this information. This means the requirements date of the components lie on one particular day although the pegged requirement is produced over a period of time (often several days). In KANBAN, you can usually take for granted that not all components have to be provided at the same time for the start date of the order. Therefore, it may be necessary to smooth the dependent requirements before calculating the control cycles. The following methods are available for smoothing the dependent requirements:

 

 

 

 

Minimum and Maximum Values for the Kanban Circulation

The result of the smoothing calculation is a smoothed requirements curve with minimum and maximum values for the number of kanbans and the kanban quantity.