Backing Up the Logical Log (Automatic) in the DBA Planning Calendar (Informix) 
Use
To avoid the logical-log files of an Informix database filling up, you can activate a triggered automatic logical-log backup in the
DBA Planning Calendar, which is part of the Computing Center Management System (CCMS). You can only follow this procedure if you use the Informix data recovery tool ON-Archive.You can create a logical-log backup for the Informix database with the DBA Planning Calendar in the Computing Center Management System (CCMS) by using the following methods:
With this you can back up the logical log including the currently used log file at the scheduled time. For more information, see
With ON-Archive you can use this method to trigger logical-log backup. This works by detecting the fill level of the logical log. When a pre-defined level is reached, the backup job triggered to run. Therefore, you must make sure that the correct tape volume is always mounted. This method offers you an extra level of security to avoid the logical log filling up.
This is the method described in this section.
SAP recommends that you use both methods for extra security. Always keep a dedicated tape drive free when backing up logs automatically.

If the logical logs are not backed up before they completely fill, you need to perform an emergency backup. This is complex, time-consuming and leads to unplanned downtime for your system. You can avoid this by devising a sensible backup schedule with the Calendar. Always make sure that the correct empty tape is loaded in the appropriate tape drive. See
Preventing Emergency Logical-Log Backup.If you need to execute a logical-log backup immediately, see
Scheduling Actions in the DBA Planning Calendar.For more information about logical-log backup, see
Logical-Log Backup.
Prerequisites
For more information about scheduling an action (for example, a logical-log backup) in the DBA Planning Calendar, see
Procedure
The percentage fill level is how full the logical-log files must be in order for a backup to be performed. A typical value might be 50%. To turn off the automatic logsave, enter 0%.
For more information, see
Volume Sets and Volumes for ON-Archive.Result
The automatic logical-log backup is now scheduled. A logical-log backup will be created when the logical log reaches the fill level you specified. For more information about looking at the results of the logical-log backup, see
Using the Archive and Backup Monitor in CCMS (Informix).