Material 

Purpose

Use this component to plan and monitor the material requirements and costs in projects, to control the flow of materials and for scheduling.

Integration

Material forms a link from a project to Sales, Materials Management (Purchasing and Inventory Management), and Production Planning and Control.

Features

Allocation

Via the allocation of material components to network activities, you determine the assemblies and raw materials that must be reserved or ordered for a project and trigger procurement via MRP or purchasing.

Depending on your type of project, there are various ways of allocating material components.

Procurement

When you allocate a material, you can determine how it is to be procured via the item category.

If a material has a long lead time (delivery or production time), you can trigger advance procurement

Scheduling Material Flow

During the scheduling of a project, the system also determines the requirements dates of the components in relation to the activity dates. This ensures that you can control and monitor the staging of the required components.

Due to the multi-level BOM explosion in networks, you can exactly control dates, since you can explain not only the top component but also all the subordinate BOM items.

Inventory Management

Material for a project can be managed in general plant stock or in individual stock. With individual stock you can follow materials that are needed for a project with regards to stock levels and MRP separately. If a network is assigned to a sales order, you can also manage the material components in sales order stock. For more information, see Managing Stocks of Material Components and Project Stock.

Delivery

If components are allocated to a project, you can create deliveries in the Project System, and as a result deliver independently of a sales order.

Via third party orders, it is possible to have externally procured components delivered directly from the vendor to the customer.