In this section you can copy cost centers to profit centers, and then change these as you wish.
The program creates a batch-input session which is used to create the corresponding profit centers.
Preconditions
You use identical numbers for cost centers and the corresponding profit centers.
You have set a controlling area.
You have already created the nodes of the standard hierarchy to which the new profit centers will be assigned.
The profit centers you are copying do not exist yet. Existing profit centers are not overwritten, since this could lead to inconsistencies.
Activities
Choose a cost center group that contains all the cost centers you want to copy. In addition, enter a name for the batch-input session.
Then import the batch-input session.
Further notes
If you want to copy an interval of cost center numbers, you can create a cost center group which contains these, and then copy that group.
Notes on transporting
You can transport the Customizing settings for Profit Center Accounting under Transport tools.