Creating a Material Cost Estimate Without Quantity Structure 
Prerequisites
Accounting and costing views exist in the material master record for the material that you want to cost. For more information, see
Material Master Records in Costing.Procedure
This brings you to: Material Cost Estimate W/o Qty Struct: Initial Screen.
-
Costing variant (see also Costing Sequence)-
Material-
Plant-
Costing lot size-
Costing version (see Working with costing versions)-
Costing date from/toThe dialog box Control Data appears.
This brings you to Create Unit Cost Estimate: list screen
If the costing variant contains a costing sheet, then overhead or process costs are calculated automatically. See also:
Result
If you created a
standard cost estimate, you can transfer the marked results into the material master record as the future standard price and the released results as the current standard price.If you created a inventory cost estimate, you can transfer the results into the material master record as the tax-based or commercial price.
If you created a standard cost estimate, inventory cost estimate, modified standard cost estimate, or a current cost estimate, you can transfer the results into the material master record as the planned prices.
See also:
Costing Results Updating the Standard Prices Tax-Based and Commercial Prices Update of Other Planned Prices