Defining a Working Time for a Position 

Use

By defining a working time for a position, you are in effect defining the reference time required for performing the tasks associated with the position in question.

If you define a working time for a position, this will override the working times defined for the organizational unit to which the position is assigned.

Procedure

To assign a working time to a position, proceed as follows:

  1. Access the organizational structure using the Organization view.
  2. Select the root organizational unit, and choose View ® Expand.
  3. Select the position for which you want to define a working time, and then choose Extras ® Working time.
  4. The Planned Working Time dialog box appears.

  5. Either enter a working time for the position, or select one of the standard working time values proposed.
  6. Choose Check.
  7. Choose Save and close.