Creating Delivery Information 

  1. On the SAP R/3 screen choose Logistics/Accounting ® Project management ® Operative structures and then Delivery Information ® Create.
  2. Enter a name for the item of delivery information and choose Continue.
  3. You can copy an existing item of delivery information an then change the copied data.

  4. Enter the project to which you want to assign the delivery information.
  5. Enter the necessary data about the delivery.

- If you want to enter a different delivery address for a goods recipient, choose Delivery address. To enter a new address, choose Create. To edit an existing address, choose Delivery address.

Selection occurs exclusively in address group PSL2, which contains addresses that have been created in deliveries from PS.

- You can only enter the organizational data all together. The three fields, S ales org., Distr. channel and Division form a sales area.

  1. If you want to assign delivery information to a WBS element, a network or an activity, choose Assignments.
  2. In the assignment overview choose Edit ® Create assignment.
  3. The Assign delivery info dialog box appears.

  4. Select the object to assign the delivery information to, enter the relevant number and choose Assign.

You can only assign delivery information to a network header in the case of header-assigned networks.

The explicit assignment of an item of delivery information to material components takes place in network maintenance. Here you choose Details ® Delivery information (see Allocating Materials to Network Manually)

  1. To change or display existing delivery information, on the Operative Project Structures screen choose Delivery information ® Change or Display.

In change mode, you can also delete delivery information, as long as no assignments exist.