Allocating Components to Other WBS Elements 

Use

You use transfer control to allocate individual material components to another WBS element.

Transfer control has two functions:

Procedure

  1. Choose Operative structures ® Tools ® BOM transfer.
  2. Choose Environment ® Transfer control
  3. Enter the material and the WBS element that you want to allocate the material component to.
  4. Save your data.

If the component is kept in project stock, the system also changes the stock segment.

If you want the requirements of the corresponding components to be consumed(if they are in project stock),they must both be assigned to the same WBS element, since requirements consumption takes place only within the same stock segment and not across projects.