Checking Material Availability 
Use
With this procedure you can check the availability of all material components allocated to a network, or the availability of an individual component.
If you change data in the network that influence the availability of material components, for instance dates or quantities, the system does not automatically trigger an availability check. To obtain current information about missing material after changes, you have to manually carry out another availability check. The same is true, if you have allocated components using
BOM transfer and have executed the allocation program again.Checking all components
In the network header, or on an activity overview, choose Edit
® Availability ® MaterialThe system checks the availability of all material components in the network. If there is a material shortage, the network receives the status material shortage. A dialog box appears from which you can go directly to the
check log, the missing parts list or missing parts overviewIn the missing parts list and missing parts overview you can also check the availability of individual components, as described below.
Checking individual components
The Confirmation Proposal screen appears on which the following data is displayed:
-
The confirmed quantity on the requested date-
The date for which the complete quantity can be confirmed-
A confirmation suggestionYou can go from this screen to the availability overview by choosing ATP quantities or display the scope availability check by choosing Scope of check.
You can display period totals or go to the detail screens of the MRP elements.

The network only receives the status material shortage if you check the availability of all components allocated to the network.