Definition
Determines how a component is procured. Depending on the item category you enter, the system may prompt you for more data.
Use
The following item categories in the R/3 System are relevant for projects:
If you allocate a component with item category L to an activity, it is procured via MRP. When
If you allocate a component with item category N to an activity, it is procured directly by purchasing, without using MRP. The system prompts you to enter the relevant purchasing data. When
This item category is used for components that are cut to size. If you allocate a material with this item category to an activity , you must also enter data for the item. The system uses this data to calculate the quantity of the variable-sized material, which is procured as item category L via MRP.
You can use the item category to assign a text of any length to an activity. Text items are not relevant for MRP.