Allocating Components to Standard Networks 

  1. Choose Logistics/Accounting ® Project management ® Basic data and then Standard structures ® Standard network ® Change.
  2. You can also allocate material to a standard network when you create the standard network.

  3. Enter a standard network and choose Activities.
  4. Select the required activities in the activity overview and choose Activities ® Component overview or choose Goto ® Comp.Overview Netwk.

If no material components have been allocated to the standard network yet, the Bill of Material dialog box appears.

If material components have already been allocated to activities of the standard network, a dialog box appears in which the corresponding BOMs are displayed.

The further procedure is the same as if no components had been allocated.

  1. You allocate material components as follows:

If several BOM alternatives exist for the material, a dialog box with the alternatives appears. Select an alternative. A list of the material allocations appears.

  1. Select the BOM items that you want to allocate and choose Edit ® New allocation.
  2. In the New Allocation dialog box, enter an activity or choose Oper/act. list to display a list of all the activities. Select an activity from the activity list.
  3. The system allocates the BOM items to the activity.

  4. If necessary repeat the last step to allocate further BOM items to other activities.
  5. Choose Back.
  6. The activity overview appears again.

  7. Save the standard network.