Replacing PRTs in Standard Networks 

  1. Choose Logistics/Accounting ® Project management ® Basic data and then Standard structures ® Standard network ® Replace functions ® PRT.
  2. The Mass Replace PRT in Networks screen appears.

  3. To change the PRT category, choose Settings ® PRT category.
  4. A dialog box appears.

  5. Select the PRT category that you want to replace.
  6. Enter the relevant data on the selection screen.
  7. Choose Execute.
  8. A dialog box appears.

  9. Enter a corresponding overview variant for the standard network.
  10. The system displays a list of all standard networks in which the production resource or tool is used.

  11. Choose Settings ® Replace with and then the PRT category.
  12. A dialog box appears.

  13. Enter the new PRT and choose Continue.
  14. Select the PRT that is to be replaced and choose Edit ® PRT.

The PRTs are replaced and the standard network is saved.