Calculation of Time Off Entitlements 
Use
The functions for calculating time off entitlements for Quota entitlements per accrual period are used for the automatic accrual of absence quotas.
The R/3 System calculates an employee’s individual time off entitlements and enters them as a deductible quota in the Absence Quotas infotype (2006).
You can base the calculation and the transfer of the accrual entitlement to the Absence Quotas infotype (2006) on a variety of different criteria.
Prerequisites
You define rules for calculating accrual entitlements in Customizing. Choose Personnel Time Management
® Time Data Recording and Administration ® QuotasFeatures
Explanation of terms: Base entitlement and base period, accrual entitlement and accrual period, transfer time
Base entitlement |
The employee’s total entitlement for a specific period. The base entitlement is a theoretical value that is used as the basis of the calculation. |
Base period |
The period for which the base entitlement is valid. |
Accrual entitlement |
The employee’s quota entitlement per accrual period, as calculated in time evaluation. The calculation is based on the base entitlement. A comparison of the base period and the accrual period converts the base period to the accrual period. |
Accrual period |
Period for which the accrual entitlement is calculated. |
Transfer time |
Point at which the accrual entitlements determined in time evaluation are transferred to the Absence Quotas infotype (2006). They increase or replace the existing value in the infotype. |

The base entitlement of 18 days is related to a base period of one year. The accrual period is 1 month. The entitlement per accrual period is 18 (days) / 12 (months) = 1.5 days per month.
In some cases, the accrual periods cannot be divided exactly in the base period. The R/3 System then calculates how often an accrual end date occurs in the base period, and uses this value as a divisor.

Employees with a seniority of 0-4 years are allocated a base entitlement of 20 days of standard annual leave, employees who have been with the company for 5-10 years receive 22 days.
If an employee’s age or seniority changes within an accrual period, this can be taken into account by the system.
You can specify a general base entitlement for all employees in a personnel calculation rule, or you can vary the base entitlement by specifying certain conditions and subrules. This allows you to base the entitlement on other master data or organizational assignments.

Employees with pay scale type 01 have a base entitlement of 2 days, employees with pay scale type 02 have 2.2 days of leave per month.


You do not want the quota entitlement to be transferred to the Absence Quotas infotype (2006) until it amounts to 12 hours.
Activities
If you want to determine accrual entitlements on the basis of hours worked, you must supply the necessary information from time evaluation. The R/3 System calculates the accrual entitlement according to an employee’s hours worked as follows:
The R/3 System uses the base entitlement to determine a theoretical accrual entitlement which the employee would be granted if he or she completed 100% of the planned hours. It then multiplies this entitlement by the current value of the day or period balance that you specified in the Set generation rules for quota selection step in Customizing.
The value of the day or period balance is determined using a personnel calculation rule. In it, the actual hours worked are divided by the planned hours in the personal work schedule. The value determined is placed in the time type.

An employee has a leave entitlement (= base entitlement) of 24 days for each year (base period). The leave entitlement is accrued monthly and placed in the Absence Quotas infotype (2006).
If the employee has completes the planned hours for each month, he or she receives an accrual entitlement of 2 days per month. The actual accrual entitlement is determined by multiplying the 2 days by the value in time type 9999.
Time type 9999 is determined from: |
80 hours of attendance 160 hours of planned time according to personal work schedule |
|
2 days of theoretical accrual entitlement if planned hours are completed |
Multiplied by value in time type 9999 = 0.5 |
Accrual entitlement is 1 day |