Separate Backflushing Processes

In this step, you define the parameters for separating the individual backflushing processes.

If you have to process a high volume of data, you can significantly improve performance by separating the backflushing processes.

For this purpose, the backflushing processes is split into critical and uncritical partial processes.
In the standard system backflushing includes all the following partial functions:

By separating the backflushing processes, you can instruct the system to post the goods receipts, and reduce the production quantities and capacity requirements immediately. The partial functions that can be carried out later (uncritical functions) are collected in a work list and processed in a background job sometime later. These uncritical functions include, for example, BOM explosion, posting goods issues, reduction of the dependent requirements and posting the production activities.