Capacity planning is carried out in Repetitive Manufacturing using the planning table. Here, you can display detailed and rate-based capacity requirements.
Requirements
To be able to display capacity requirements for run schedule quantities and planned orders in the planning table, you must first make sure that the following prerequisites have been fulfilled:
Standard settings
In Repetitive Manufacturing, you have two options for carrying out capacity leveling:
Capacity profiles control exactly how the capacity data in the planning table is displayed and which strategy is used in the capacity planning table to dispatch operations. You maintain these profiles in Customizing for Capacity Planning under capacity leveling. Here, you can maintain total profiles that consist of individual profiles. In the standard system, a profile exists for the planning table (SAPREMG001) and for processing both planning tables simultaneously.
If you want to define your own profiles, you can enter a profile in the user master record under the parameter ID KP1. The system then uses this profile instead of the standard profile for the planning table. If you save a profile under parameter ID KP2, the system then uses this profile when processing both planning tables simultaneously.
When creating your own profile for planning both tables simultaneously, note that a periodic and a time continuous layour is allowed for the assigne control profile. You define this layout by setting the indicator layout category 3 in the control profile.
You can refer to the Implementation Guide for Capacity Planning to find out which data is saved in the profiles. Note that you should only make changes to profiles in special circumstances. Necessary changes may include:
Further notes
In the capacity planning table, the system splits the screen into two sections. In the upper section of the screen, the system displays all dispatched planned orders and production orders per production line and capacity category. In the lower section of the screen, the system displays all the capacity requirements for the materials that can be produced on the selected lines (this display includes the dispatched and the non-dispatched orders). You cannot change this split display.