Scheduling Changes to a Material Master Record
The initial screen appears.
If you want to refer to a change number, enter one in the appropriate field. The date from which the change is to be valid must be in the future and not precede the valid-from date of the change number.
Choose Enter.
The Select View(s) dialog box appears.
Select the user departments whose material data you want to change and choose Enter.
The Organizational Levels dialog box appears.
Enter your organizational levels and choose Enter.
The first data screen appears.

Scheduled changes must be activated. See Activating Scheduled Changes.